Progress bar for C0002 commands (from V8.0 onwards)

Functional description
In the Engineer from V2.12, commands which can be activated via C002 have a progress bar. That way, the user is given a feedback on the fact that the command is still running and on how much time is still required approximately.

Applications
C0002 commands are frequently used particularly for commissioning. The progress bar is very helpful here due to the various execution durations. Furthermore, code C008 (progress device command) can be read by a higher-level control to start other activities not until the device command has been completed.

Included in which products/versions?
From Engineer 2.12 and firmware V08.00.24.00


Published in Service Message No. 26/2010

URL for linking this AKB article: https://www.lenze.com/en-de/go/akb/201009924/1/